DIN Rail Power Supply Selection Checklist
Selection, mounting and testing checks for a DIN rail power supply feeding a low-voltage control panel.
A real, editable checklist below — tick, tap a line to rewrite, drag to reorder.
Tick the circles, tap any line to change it, drag the dots to reorder.
Saved in this browser. Send it to Clear to keep it on your phone.
Get this list on your phone
Point your phone's camera at the code.
This list is for panel builders, OEM buyers and technicians choosing a DIN rail power supply for a control cabinet. Name the model, not just the wattage: a '120 W DIN supply' leaves out output voltage, current rating, terminal layout and approvals. Advantech's range spans 12, 24 and 48 V outputs. The checks below follow selection, mounting, wiring and acceptance testing for low-voltage control loads. They leave out motor drives, battery chargers and household AC supplies, and they don't replace the manufacturer's instructions.
Why these items are on the list
- Define the electrical boundary. Decide which loads share the control bus. Motors and heaters need their own engineered circuits.
- Specify the exact model. Variants differ in output voltage, current rating, terminal arrangement and approvals.
- Confirm output voltage. Match the supply to your devices' approved voltage ranges, such as a 24 V bus.
- List each load's current. Record the approved voltage range, normal current and startup demand for every device.
- Sum simultaneous current. Count loads that overlap during mains restoration, startup, alarms and output actuation.
- Allow for startup demand. A normal running average can hide the most demanding state.
- Check output against the load. WEHO documents the NDR-120-24 at 24 V, 5 A, a 120 W limit. Validate dynamic and thermal duty separately.
- Compare input ranges. Label and specification wording can differ. Confirm the ordered revision, and don't assume DC-input operation.
- Review ambient temperature. Check air temperature around the supply and neighboring heat sources, not only room temperature.
- Confirm standard 35 mm rail. The NDR-120 drawing references TS35 rail. Confirm rail retention on the actual assembly.
- Check case dimensions. WEHO's NDR-120 drawing gives 40 mm width, 125.2 mm height, 113.5 mm depth. Case sizes aren't clearances.
- Reserve installation clearance. Leave room for conductor bends, terminal access, convection, rail engagement and safe removal.
- Mount in documented orientation. WEHO's NDR-120 guidance: keep it upright, front label accessible, rear interface engaging the supported DIN rail.
- Read the terminal layout. WEHO warns duplicated DC terminals aren't evidence of independent protected channels. Never use ventilation openings for cable entry.
- Coordinate branch protection. Select protection and conductors together. Supply protection doesn't replace branch protection.
- Calculate voltage drop. Include outgoing and return conductor resistance, connectors and temperature effects.
- Never raise adjustment to hide cable resistance. Don't raise the adjustment setting to conceal excessive cable resistance; measure voltage at the most demanding remote load.
- Measure at the far-end load. Check voltage at the supply and the most demanding remote load during startup.
- Repeat tests when warm. Repeat relevant tests after thermal stabilization.
- Request ordered-variant documents. Ask for the approved specification, mechanical drawing, label confirmation and compliance evidence.
- Verify certifications. A CE marking alone doesn't establish every certification a customer's market requires.
- Log the tested configuration. Record input conditions, steady and peak current, panel temperature, recovery behavior and exact model.
- Use qualified personnel for wiring. They follow the ordered product's instructions for isolation, conductor selection, stripping and torque.
Tick each check at the cabinet on your phone, then hand the list to a second person to review before you order.
When to use it
Use it when specifying a power supply for a new or replacement control panel, before you place the order.